Posted on: June 15, 2017

River East Project Update - Curb & Gutter going in tomorrow!

River East construction crews will are preparing for the installation of curb & gutter and driveway aprons. The subcontractor will begin pouring tomorrow. Residents will not have access to the newly poured driveway aprons for 3-5 days to allow concret...

Read on...

Posted on: June 9, 2017

River East Update - Weekend Parking

Construction crews are finishing up their work for the week and will leave the municipal parking lot along N. 2nd Street open and available to accommodate visitors to the St. Thomas Country Fair. Fair goers can also access the new Elizabeth Street parking...

Read on...

Posted on: June 7, 2017

River East Project Update - 6-7

Work continues in the municipal lot, but it remains open & accessible. Water trucks will be coming in soon as the drier weather, along with excavation on N. 2nd and Division has led to problems with excessive dust.

Posted on: June 1, 2017

River East Project Update

parking improvements

South entrances to the municipal parking lot are closed. Access lots by using the driveway north of the Fire Station, traveling behind the station. Caution is urged as construction on the lot continues.

 N. 2nd St beginning at Main will be closed ...

Read on...

Posted on: May 31, 2017

River East Parking Update - N. 2nd Closed; Limited parking and access in lot

Access to the municipal lot and available parking will be limited this week. Private parking behind E Main St businesses will be open to those property owners, but municipal stalls at the north end of that area will be closed possibly to Wednesday. N. 2nd...

Read on...

Posted on: May 25, 2017

Municipal Lot to Close on Tuesday

We’ve just learned that construction work necessitates closing the municipal parking lot adjacent to N. 2nd Street until further notice. The lot will be open through the holiday but will close first thing Tuesday morning. Limited parking will st...

Read on...

Posted on: May 25, 2017

River East Construction Update 5-25

Absolutely Waterford’s Economic Committee has been meeting to discuss ways to mitigate the challenges businesses face during major road construction projects. While the River East project is smaller in scope than the upcoming Main Street utility...

Read on...

Posted on: May 24, 2017

River East Construction Update for 5-24

Despite challenges posed by rainy weather, crews are making great progress.

  • Storm sewer work in the area is completed
  • Grading of the N 2nd St parking lot is underway as crews begin from the Fire Station and progress to the south. The parking lot will be ope...
Read on...